Portion of Trafalgar Parkway Closed Starting November 1

October 18, 2023

UPDATE:  November 2, 2023
The contractor will begin the project on November, 1; however, the work will be performed at night.  Night construction activities normally run from 7 p.m. to 7 a.m.  Construction is scheduled to take place November 1, 2 and 3 and November 6, 7 and 8.  On November 6, 7, and 8 work will take place during the daytime and nighttime hours.  

During construction detours will be in place, and accommodations will be made for local traffic.

Work is subject to change due to weather conditions.  Work is expected to be complete by the end of next week.

Drivers, bicyclists, and pedestrians should use caution while traveling through the area. 


Trafalgar Paving Project